Lag time
Resolved · Low Priority · Version 2007
RE: lag time
Hello Madeline,
Hope you enjoyed your Microsoft Project Intro Intermediate course with Best STL.
Thank you for your question regarding lag and lead time.
Lag and lead time enable you to be specific about the time relationships between your tasks. You can set up gaps between linked tasks, or have them overlap.
Lag time is a delay between tasks that have a dependency. For example, if you need a two-day delay between the finish of one task and the start of another, you can establish a finish-to-start dependency and specify a two-day lag time [entered as a positive value].
Lead time is an overlap between tasks that have a dependency. For example, if a task can start when its predecessor is half-finished, you can specify a finish-to-start dependency with a lead time of 50 percent for its successor [entered as a negative lag value].
I hope this resolves your question. If it has, please mark this question as resolved.
If you require further assistance, please reply to this post. Or perhaps you have another Microsoft Office question?
Have a great day.
Regards,
Rodney
Microsoft Office Specialist Trainer
Fri 26 Nov 2010: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Autofit column width – Project (all versions)At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move. |