Resource Costs

resolvedResolved · Medium Priority · Version 2007

Nisha has attended:
Project Intro Intermediate course

Resource Costs

Where and how should you handle resources that have a fixed daily rate? They cost of the resource (fixed) will be independednt of tasks they are assigned to and whether they are over or inder allocated. Thanks

RE: Resource Costs

Hi Nisha,

Thank you for your question.

I would apply the Cost Table to the Gantt Chart view and then add the amount of the resource fixed cost in the second column which is Fixed Cost.

I hope this answers your question.

Regards

Simon

Thu 2 Sep 2010: Automatically marked as resolved.


 

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)