Linking sucessors to split tasks
Resolved · Urgent Priority · Version 2007
Sabine has attended:
Project Intro Intermediate course
Linking sucessors to split tasks
What successor format must you use to get a successor to happen every time a part of a split task is performed?
RE: linking sucessors to split tasks
Hi Sabine
Thank you for your question. Project will only let you connect to the start or finish of the whole task, not to the start or finish within a task that has been created as a result of a split.
You can get close to the effect you are looking for by first creating a summary task and then making several sub tasks below it (rather than splitting one larger task down).
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
Wed 16 Jun 2010: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Autofit column width – Project (all versions)At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move. |