Is there an easier way to change the task durations in my current plan from weeks/months to days without changing it individually?
RE: MS Project
Hi Joyce
Thanks for your question. Yes there is, it will save you a lot of time.
There is a macro that ships with Project designed to change all durations to the unit you prefer.
If you go to Tools > Macro > Macros highlight the Format_Duration macro and click run. It will ask you what duration you want to use and re-format all the task durations to the unit you selected.
Hope this helps.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Using the Quick Access Toolbar in Project 2010The Quick Access Toolbar is included in virtually every Office product, including Project 2010 as well as Outlook 2010, Word 2010, Excel 2010, and PowerPoint 2010. |