Forum home » Delegate support and help forum » Microsoft Project Training and help » Change to standard calendar or change to resource working hours?

Change to standard calendar or change to resource working hours?

resolvedResolved · Medium Priority · Version 2007

Caroline has attended:
Project Intro Intermediate course

Change to standard calendar or change to resource working hours?

I oversee the timelines etc for 5 software developers who all work on several projects.

On the whole the decision has been taken to schedule them to work a 6 hour day (to take into account various factors that mean it is near on impossible to actually work a solid 8 hr day when developing). So for example if we quote a client '1 days work' I will be scheduling the developers for 8 hours - so this will span a day and a couple of hours. However, (typically this isn't always going to be the case) - as we do have the odd contract that has the developer on site for a specified number of days, so in this instance I would want the 'standard' calendar to apply.

My ideal is to have a resource sheet, then each project bought together on a master project - pulling the resource allocation through from the resource sheet.

My only confusion at the moment is whether I change the standard calendar on each project (or create a template to work from) showing this 6 hour working day, or if I should change each of my resources to show they only work a 6 hour day...?

Then what would I do in the instance where the six hour day doesn't apply?

hope that makes sense!

Caroline

RE: Change to standard calendar or change to resource working ho

Hi Caroline

Because you mentioned you plan 1 day with clients as 8 hours but your developers allow 6 per day you might want to leave the standard calendar using 8 hours.

You could then create a special calendar called "6 hour day", that has hours reduced from the standard 8 hour day. Then set your resources on the Resource sheet to follow the 6 hour day calendar rather than standard.

Build your project and assign your resources. Once resources are assigned you will see how long the project will take. This also makes it easy to incorporate resources that do work 8 hours.

For those tasks that should run at 8 hours per day even though developers have been assigned - double click on the task name then in the advanced tab set the Calendar for that task to Standard and tick the box "Scheduling ignores resource calendar". Now everyone working on this task will work 8 hours per day regardless of their own base calendar.

There may be other ways to achieve this but does this get you closer to the result you are seeking?

Kind regards,
Andrew


 

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.