98.7% Of all customers recommend us, we're so confident about our results we publish all reviews and stats
View Live Stats View ReviewsForum home » Delegate support and help forum » Microsoft Project Training and help » microsoft+project+training - Milestone
microsoft+project+training - Milestone
Resolved · Low Priority · Version Standard
Luke has attended:
Project Introduction course
Project Introduction course
Milestone
How do I create the above?
RE: Milestone
Luke,
Thanks for the question.
To create a Milestone, enter a zero 0 day in the duration part of the task.
Good luck
Regards, Rich
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Entering DaysTo type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date. |