MSProject - Resourcing

resolvedResolved · Low Priority · Version 2007

Yelena has attended:
Project Intro Intermediate course

MSProject - Resourcing

Can the projects of several resources be combined into one overall project plan?

RE: MSProject - Resourcing

Hi Yelena

Thank you for your question. Yes they can by putting all the resource details into a plan (which becomes the Resource Pool). Then in each plan that needs to use members of that team go to the Tools menu and choose Resource Sharing > Share resources. Select the option to use resources from the Resource pool and now you will be able to assign resources from the Resource Pool to tasks in your project.

I hope this helps do let us know if you have any further questions.

Kind regards,
Andrew

Tue 29 Dec 2009: Automatically marked as resolved.


 

MS Project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.