Split tasks in Project

resolvedResolved · Low Priority · Version 2003

James has attended:
Project Intermediate course

Split tasks in Project

Is there a way of giving a penalty for splitting a task. E.g. There is time associated to setting up a task which recurs every time a task is re-started.

RE: Split tasks in Project

Hi James,

Thank you for your question.

There is no easy way of achieving this.

The only method I can think of is to manually enter the time in Resource Usage view.

I hope this helps.

Regards

Simon

Thu 10 Dec 2009: Automatically marked as resolved.


 

MS Project tip:

Set default task type - Project 2010

a. In Project, click on the File tab
b. Select Options from left hand side
c. Click on Schedule to set the scheduling options
d. Set the Default Task type box to your chosen option
i. Generally if you plan/estimate your projects using durations you should use fixed duration, and untick the box New tasks are effort driven, if you plan/estimate with person hours use fixed work, or for plans estimated with the proportion of resources time use fixed units, and untick the box New tasks are effort driven)
e. Click OK to apply your changes