changing working time weekends

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » Changing Working Time to Weekends

Changing Working Time to Weekends

resolvedResolved · Low Priority · Version 2003

Jen has attended:
Project Intro Intermediate course

Changing Working Time to Weekends

How can I set a new Calander for Working over the Weekends in Change Working Time?

Many Thanks

Jen

RE: Changing Working Time to Weekends

Hi Jen

Thank you for your question - you can create a new calendar by going to Tools > Change working time then click on the New button.

You get to choose whether the new calendar is based on an existing calendar (and will inherit that calendar's non working time settings) or is a new calendar.

Once you have made your choice you can customise the calendar by clicking on the column labels for Saturday and Sunday and marking the days as Non standard working time.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew

Generic Terms for Resources

Thankyou, that was very helpful.

My other problem is that I have started to use generic terms for resources as groups of resources share particular jobs and move around those jobs. However Project will not let me use the generic term more than once for a specific task e.g. I may need 2 of 'Taxonomist A'. I have assigned this resource 600% as there are 6 Taxonomist A's. Is there any way around this?

Thnaks again,

Jen

RE: Generic Terms for Resources

Hi Jen

Thank you for your question - the ideal way would be to assign 200% of your resources to a task to indicate 2 of the 6 are working on an activity. That should leave the other 4 available for working taking place on the same day.

I hope this helps.

Kind regards,
Andrew

RE: Generic Terms for Resources

Ah excellent! that works well. Many Thanks again!


 

MS Project tip:

Set default task type - Project 2010

a. In Project, click on the File tab
b. Select Options from left hand side
c. Click on Schedule to set the scheduling options
d. Set the Default Task type box to your chosen option
i. Generally if you plan/estimate your projects using durations you should use fixed duration, and untick the box New tasks are effort driven, if you plan/estimate with person hours use fixed work, or for plans estimated with the proportion of resources time use fixed units, and untick the box New tasks are effort driven)
e. Click OK to apply your changes

View all MS Project hints and tips


Server loaded in 0.09 secs.