98.7% Of all customers recommend us, we're so confident about our results we publish all reviews and stats
View Live Stats View ReviewsForum home » Delegate support and help forum » Microsoft Project Training and help » Duration changing when marking a task as complete | MS-Project forum
Duration changing when marking a task as complete | MS-Project forum
Resolved · Medium Priority · Version 2003
Samantha has attended:
Project Intro Intermediate course
Project Advanced course
Duration changing when marking a task as complete
Sorry, me again! I wonder if you can help me?
I am working on a project where I have start, finish and I have recently added an actual finish column.
When I marked my milestones as being completed on the day they were scheduled to be completed it changed the duration from 0 days to 1 day. How can I ensure that this doesn't happen, I think it has something to do with setting timeframes but when I've looked in that area (Tools/Options) I can't work out what I'm supposed to do!
Thanks in advance.
Sam
RE: Duration changing when marking a task as complete
Hi Samantha,
Thank you for your question.
Are you marking the task complete by using the Actual Finish column?
If so, you can use the Actual Start and Actual Finish column to fill in actual dates when a task doesn't start or finish as scheduled. This is why it is changing the duration.
In future try adding the %complete column to mark tasks that are completed as scheduled. This should stop the milestones from changing their duration.
I hope this answers your question.
Regards
Simon
RE: Duration changing when marking a task as complete
Thanks for your response Simon.
I've been told that for the purposes of setting up reports I need to have Scheduled Start, Scheduled Finish, Baseline Finish and Actual Finish.
My manager thinks that this is something to do with how the times are set up that MS Project is making my milestone 1 day instead of 0 and when I have a task scheduled to finish on 26/02 and actual finish is 27/02 it is saying that the task took 2 days rather than just 1... is there any way I can sort that out?
Thanks in advance
Sam
RE: Duration changing when marking a task as complete
Hi Samantha
Just wanted to check to see how you are getting on with marking your tasks as complete. The simplest way would be to set the percentage complete to 100% (by double clicking on a task and setting the percentage on the general tab to 100). This should leave the duration unchanged.
Let us know if you are still having problems.
Kind regards,
Andrew
Wed 2 Sep 2009: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Giving Someone a Gantt Chart SnapshotTo pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010) |