Reporting RAG against % task complete in Project | MS-Project forum
Resolved · Medium Priority · Version 2003
Samantha has attended:
Project Intro Intermediate course
Project Advanced course
Reporting RAG against % task complete in Project
Hi there
I'm not sure whether this is possible... I think it might be but can you tell me if I can insert a column to show RAG status on how complete a task is?
Thanks
Sam
RE: Reporting RAG against % task complete in Project
Hi Samantha, this is certainly possible but a little difficult to answer completely in a post here. However, have a look at the following thread on this forum:
http://forums.techarena.in/microsoft-project/1001679.htm
...which should point you in the right direction!
Hope this helps,
Anthony
RE: Reporting RAG against % task complete in Project
Thanks Anthony. What I'm trying to achieve is much simpler than this I think...
I am going to be manually changing the % complete column and I just want a formula to show the following:
C = 100%
G = 80-99%
A = 50-79%
R = 0-49%
I'm challenged when it comes to formulas so any further assistance would be fantastic.
Thanks
Sam
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Gantt ChartsGantt Charts was first Invented by Henry Gantt (1861-1919) while planning the construction of U.S. Navy ships during WWI.hence the name Gantt Charts |