project.training - milestone

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » project.training - Milestone

project.training - Milestone

resolvedResolved · Low Priority · Version Standard

Sally has attended:
Project Intro Intermediate course
Project Intro Intermediate course

Milestone

How do I create above

RE: Milestone

Sally

Thanks for the question

Enter a zero 0 day in the duration part of the task

Good luck

Tracy


 

MS Project tip:

Format individual bars on your GANTT chart

To draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications.

View all MS Project hints and tips


Server loaded in 0.07 secs.