tasks

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » Tasks

Tasks

resolvedResolved · Low Priority · Version 2003

Gareth has attended:
Project Introduction course

Tasks

What is priority

RE: Tasks

Hi Gareth,

Thank you for your question.

When you create a task, in the task information box you can set a priority level of between 1 and 1000.

When you assign resources to a task, sometimes you will assign a resource to two jobs on the same day. Project will mark that resource as overallocated.

If Resource Levelling is used to resolve the overallocation, the lower the number, the more likely the task will be delayed to resolve the problem.

I hope this answers your question.

Regards

Simon

Wed 10 Jun 2009: Automatically marked as resolved.


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips


Server loaded in 0.09 secs.