Time Periods
Can you please let me know if it is possible to create a programme using hours as a timeline rather than days? (ie) for a short term project over 5 days with multiple tasks that require 10 or more tasks to be completed within a day.
When using the timeline as days I know you can reduce the period to complete to 0.25 days but this is not very visually effective when printed.
RE: Time Periods
YES
On the Tools menu, click Options, and then click the Schedule tab.
Under Scheduling options for, in the Duration is entered in list, click a duration unit.
To use the same setting automatically in all future projects, click Set as Default.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Show or hide toolbar ScreenTipsOn the Tools menu, go to Customize, and then select Toolbars. |