Time Periods

Can you please let me know if it is possible to create a programme using hours as a timeline rather than days? (ie) for a short term project over 5 days with multiple tasks that require 10 or more tasks to be completed within a day.

When using the timeline as days I know you can reduce the period to complete to 0.25 days but this is not very visually effective when printed.

RE: Time Periods

YES
On the Tools menu, click Options, and then click the Schedule tab.
Under Scheduling options for, in the Duration is entered in list, click a duration unit.
To use the same setting automatically in all future projects, click Set as Default.


 

MS Project tip:

Show or hide toolbar ScreenTips

On the Tools menu, go to Customize, and then select Toolbars.
Click the Options tab.
put a tick or remove the tick from the Show ScreenTips on toolbars check box.