Project
Resolved · Medium Priority · Version 2007
Myrtle has attended:
Project Intro Intermediate course
PowerPoint Introduction course
PowerPoint Intermediate Advanced course
Excel Introduction course
Excel Intermediate course
Access Introduction course
Access Intermediate course
Project
How to import a project into excel
RE: Project
Hi Myrtle,
Thank you for your question.
Open the project and follow these instructions:
1. File and Save as.
2. Change the File Type to Excel Workbook and name the file.
3. Click next to start the wizard.
4. Select new map and then choose what data you want exported.
5. Select the fields you want from the project file and name the fields they will be exported to in Excel.
6, Save the Map if you wish.
7. Click Finish.
I hope this answers your question.
Regards
Simon
Thu 9 Apr 2009: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Avoid Accidental ConstraintsThe initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.) |