Percent complete

resolvedResolved · Low Priority · Version 2003

Nancie has attended:
Project Intro Intermediate course

Percent complete

Which is the best choice to complete percent complete? Physical, work or percentage to show 100% complete or does it matter?

RE: Percent complete

Hi Nancie,

Thank you for your question.

When you update a value in the Actual work column it will calculate the % work complete. There is no best answer as each of these methods can used in different situations.

The following link gives you an insight to what these methods are used for.

tp://www.mpug.com/News/Pages/TrackProjectProgresswithPhysicalComplete.aspx

I hope this helps.

Regards

Simon

Thu 9 Apr 2009: Automatically marked as resolved.


 

MS Project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.

View all MS Project hints and tips


Server loaded in 0.09 secs.