Calculations
can i add my own calculated fields
RE: calculations
Hi Megan,
Thank you for your question.
Go to Tools, Customize and Fields. You can create formulas based on Tasks or Resources.
The next step is to insert the field you have just created.
I hope this answers your question.
Regards
Simon
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Link tasks using predecessor column - projecta. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number. |