How do you change the Start date of your project?

RE: Dates

Hi Aldo

Thank you for your question. If you are part way through planning your project and you want to change the start date turn on the Analysis toolbar (View > Toolbars > Analysis) then click on the Adjust date button and enter your new date.

I hope this is helpful - do let us know if you have any further questions.

Kind regards,
Andrew

Tue 10 Mar 2009: Automatically marked as resolved.


 

MS Project tip:

Create own ribbon tab - Project 2010

a. In Project click on the File tab
b. Select Options from left hand side
c. Choose the Customize Ribbon section
d. Click the New Tab button (below the list of tabs on the right hand side of the dialog box)
e. Select the New Tab (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
f. Select the New Group (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
g. Add commands to your tab and group by locating them on the list on the right hand side (remembering that you can change the list using the drop down box at the top of the list of commands) and clicking the Add button between the two panes to add them to your tab and group
h. You can rearrange the commands in your group, the groups on any tab or the tabs, using the up and down arrow buttons beside the list of tabs.
i. Click OK to apply your changes