Lag
Resolved · Low Priority · Version 2007
RE: Lag
Hi Dee
Thank you for your question.
Lag can be added by double clicking a successor task and switching to the predecessor tab then adding the required amount of delay in the lag column.
You can also access the same field by double clicking the arrow connecting the predecessor and successor.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
Wed 25 Feb 2009: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Using the Quick Access Toolbar in Project 2010The Quick Access Toolbar is included in virtually every Office product, including Project 2010 as well as Outlook 2010, Word 2010, Excel 2010, and PowerPoint 2010. |