What is the relationship between DURATION and WORK CONTENT.
RE: Project 2007
Hi Norman
Thank you for your question. The Duration represents how long you will allow for something to take place and Work represents the amount of activity that resources will carry out during that time.
For example you might allow 5 days duration to produce a report. During that time the total work required might be 10 hours.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Inserting Task Durations QuicklyWhen entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day. |