Costs
How to add plant, labour and material cost, to a project on MS project, if possible?
RE: Costs
Hi Aaron
The resource sheet view stores work and material resources, their costs and related information.
Resources can then be assigned from the Gantt chart view (click on the assign resources icon), select the task and resource then click assign.
Any costs associated with the resource will be rolled up to reflect the duration/work of the task.
Hope this helps,
let us know if you have any further questions.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Link tasks using predecessor column - projecta. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number. |