ms+project+training - costs

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » ms+project+training - Costs

ms+project+training - Costs

resolvedResolved · Low Priority · Version Standard

Aaron has attended:
Project Intro Intermediate course

Costs

How to add plant, labour and material cost, to a project on MS project, if possible?

RE: Costs

Hi Aaron

The resource sheet view stores work and material resources, their costs and related information.

Resources can then be assigned from the Gantt chart view (click on the assign resources icon), select the task and resource then click assign.

Any costs associated with the resource will be rolled up to reflect the duration/work of the task.

Hope this helps,

let us know if you have any further questions.

Kind regards,

Andrew


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips


Server loaded in 0.07 secs.