Forum home » Delegate support and help forum » Microsoft Project Training and help » Activity

Activity

resolvedResolved · Low Priority · Version 2003

Michael has attended:
Project Introduction course
Project Intermediate course

Activity

How do I add a sub-activity to a summary activity

RE: Activity

Hi Michael

Whenever a task is indented (the right facing arrow on the second toolbar) it becomes a sub item of the first non-indented task above it.

I hope this helps - let us know if you have any further questions.

Kind regards,
Andrew

Tue 3 Feb 2009: Automatically marked as resolved.


 

MS Project tip:

Set default task type - Project 2010

a. In Project, click on the File tab
b. Select Options from left hand side
c. Click on Schedule to set the scheduling options
d. Set the Default Task type box to your chosen option
i. Generally if you plan/estimate your projects using durations you should use fixed duration, and untick the box New tasks are effort driven, if you plan/estimate with person hours use fixed work, or for plans estimated with the proportion of resources time use fixed units, and untick the box New tasks are effort driven)
e. Click OK to apply your changes