Project
Resolved · Low Priority · Version 2003
Mark has attended:
Project Introduction course
Project Intermediate course
Project
How do I intepret the "critical path"?
RE: Project
Hi Mark
Thank you for your question. You can quickly see the critical path by looking at the Tracking Gantt view. Tasks coloured red are considered critical by the software. Critical tasks are those that are controlling the end date of the project and have no slack or float around them. This means that if something changes in the duration of a red task then the end date of the project will also change (positively or negatively).
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Change default view – Project 2010a. In Project, click on the File tab |