Ms manager
Resolved · Low Priority · Version 2003
RE: ms manager
Hi Kevan
Thanks for your question.
You can create a Project Summary Task by going to Tools > Options and choosing the View tab. In the lower right corner there is a setting to turn on the project summary task.
You can create a summary task by indenting the task directly below it in the table.
I hope this is helpful - let us know if you have any further questions.
I hope this is helpful
Kind regards,
Andrew
Tue 3 Feb 2009: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Compare Work and DurationDuration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field. |