ms manager

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » Ms manager

Ms manager

resolvedResolved · Low Priority · Version 2003

Kevan has attended:
Excel Introduction course

Ms manager

How do I create a summary

RE: ms manager

Hi Kevan

Thanks for your question.

You can create a Project Summary Task by going to Tools > Options and choosing the View tab. In the lower right corner there is a setting to turn on the project summary task.

You can create a summary task by indenting the task directly below it in the table.

I hope this is helpful - let us know if you have any further questions.

I hope this is helpful
Kind regards,
Andrew

Tue 3 Feb 2009: Automatically marked as resolved.


 

MS Project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.

View all MS Project hints and tips


Server loaded in 0.08 secs.