Does MSP have an auto sort function?

RE: MS Project

Hi Christopher

Project does enable you to sort your plan. From the Project menu choose Project > Sort and then choose one of the built in sort fields or click on sort by... to select your own sort fields.

I hope this helps - do let us know if you have any more Project questions.

Kind regards,
Andrew

Tue 3 Feb 2009: Automatically marked as resolved.


 

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)