Where do we get the manual?

RE: Manual

Hi Mike,

Thank you for your question.

If you go to www.stl-training.co.uk and click on Delegate Sign In in the top right of the page.

Type in your email address and 4 digit password to access your account. Navigate to the bottom of the page and you will see the course you attended highlighted in green. There are 4 yellow zipped folders which contain the manuals for the course. Hover over each folder and find the 2003 folder and then click on it to download and save to your pc or laptop.

I hope this answers your question.

Regards

Simon

Mon 19 Jan 2009: Automatically marked as resolved.


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips