How do you view a critical path

RE: Project 2003 - How to view a critical path

Hi Linda,

Thank you for your question.

There are a few ways to view the critical path:

1. Use the Gannt Chart Wizard to format the Critical Path.
2. Change your view to Tracking Gannt.
3. Use Filtering to show the tasks on the Critical Path.

I hope this answers your question.

Regards

Simon

Mon 12 Jan 2009: Automatically marked as resolved.


 

MS Project tip:

MS Project 2010 Scroll to Task

Ever feel lost on a large project file? In Gantt view, Task ribbon, Editing, click on the Scroll to Task tool to centre the task bar on your screen.

Shortcut Ctrl+Shift+F5

Same as Go to Selected Task in MS Project 2003.

View all MS Project hints and tips


Server loaded in 0.07 secs.