RE: Project
Hi Linda
Thanks for your question. The baseline captures values relating to your activities (including start, finish, duration, work and cost) so that you can compare your starting and current positions to identify slippage.
The tracking Gantt view (View > Tracking Gantt) shows the baseline below your live project as grey task bars.
I hope this helps - let us know if you have any further questions.
Kind regards,
Andrew
Wed 10 Dec 2008: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Project Communityin the help menu type "Tips" then select "Ask the Project community" this takes you into microsofts site where you can ask questions to lots of knowledgeable people.They make up an online group of experienced Project users who answer questions and provide solutions and tips. |