Forum home » Delegate support and help forum » Microsoft Project Training and help » Leveling

Leveling

resolvedResolved · Low Priority · Version 2003

Tracey has attended:
Project Intermediate course

Leveling

What is the meaning of 'Level resources with proposed booking type'

RE: Leveling

Hi Tracey,

Thank you for your question.

The Booking Type field is only used in conjunction with Microsoft Project Server.

It specifies whether a resource is committed to the project (which is like writing their name in ink) or the resource is
proposed on the project (which is like writing the resource name in pencil) which means you can easily rub it out if they are not used.

I hope this answers your question.

Regards

Simon.


 

MS Project tip:

Formatting Bar Text

To display notes or resource initials on the Gantt chart bars, choose Format, Bar Styles and the Text tab. Select the position you want to show the text i.e. Top or Inside etc, then choose the field name you are looking for from the drop down arrow. Type the first letter of the name to get quickly to the top of the letter range. Click OK.