Resources
Is it possible to show all the work someone has been assigned across multiple projects?
RE: Resources
Hi Beth
Thanks for your question. Yes it is possible. To do this first create a project file that just contains your resource information. This is now your resource pool. Keep the resource pool and open your project file that needs resources. From the Tools menu choose resource sharing > share resources and choose the option to use resources from the resource pool. Repeat this process with the rest of your projects.
To see a combined overview of resource assignment across all of your plans take a look at the resource usage view in your resource pool
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Using the Quick Access Toolbar in Project 2010The Quick Access Toolbar is included in virtually every Office product, including Project 2010 as well as Outlook 2010, Word 2010, Excel 2010, and PowerPoint 2010. |