How do i make sure that my project executive is not assigned to tasks for wednesdays and thursdays as he works part time?

RE: calendar

double click on your project executive resource and select the working time tab and and select wednesdays and thursdays heading , then select Non working time radio button to the left of the dialog box


 

MS Project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.