ms project courses london - Calendar
Resolved · Low Priority · Version Standard
Emma has attended:
Project Intro Intermediate course
PowerPoint Intermediate Advanced course
Calendar
How do i make sure that my project executive is not assigned to tasks for wednesdays and thursdays as he works part time?
RE: calendar
double click on your project executive resource and select the working time tab and and select wednesdays and thursdays heading , then select Non working time radio button to the left of the dialog box
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Typing Links Between TasksIn the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between. |