How can you link different projects together?

RE: Microsoft Project

Hi Sanjay

Thanks for your question. A quick way to join projects together is to create a temporary blank project then from the insert menu choose to insert the projects you would like to link. Once they are all assembled use the mouse to drag links between the tasks you would like to link. Double click on the links you have added to change them to other types of connection (eg SS, FF etc) if necessary.

Now close your combined project and save changes to all the files. The sub projects are linked and you can discard the temporary overall file.

I hope this helps - let us know if you have any further questions.

Kind regards,
Andrew


 