What is the difference bewtween the schedule and the actual with reference to the GANTT

RE: MS Project

Hi Peter

Thanks for your question. Schedule values refer the the plan as laid out in the Chart. They show how you anticipate the project will unfold. Actual values refer to progress and capture what has really taken place. The appear in the Gantt chart as a black line drawn through the bar of the task. The length of the black line represents how much of the task has been completed (usually a representation of the percentage duration complete)

I hope this helps - let us know if you have any further questions.

Kind regards,

Andrew


 

MS Project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)

View all MS Project hints and tips


Server loaded in 0.09 secs.