Forum home » Delegate support and help forum » Microsoft Project Training and help » Project 2003

Project 2003

resolvedResolved · Medium Priority · Version 2003

Theresa has attended:
Project Intro Intermediate course
Excel Advanced course

Project 2003

How do you create new views? I want to create several new views and I'm aware that you use the organiser facility but I can't remember all of the processes.

RE: Project 2003

Hi Theresa

Try View > More Views > New (or copy an existing view) to build a fresh view. If you want it to appear in the view bar then make sure you check that option in the dialog box when you configure your view.

Hope this helps - let us know if you have any other questions.

Kind regards,

Andrew


 

MS Project tip:

Set default task type - Project 2010

a. In Project, click on the File tab
b. Select Options from left hand side
c. Click on Schedule to set the scheduling options
d. Set the Default Task type box to your chosen option
i. Generally if you plan/estimate your projects using durations you should use fixed duration, and untick the box New tasks are effort driven, if you plan/estimate with person hours use fixed work, or for plans estimated with the proportion of resources time use fixed units, and untick the box New tasks are effort driven)
e. Click OK to apply your changes