Linking different project plans
Resolved · Low Priority · Version 2003
Kamilla has attended:
Project Intro Intermediate course
Linking different project plans
Is it possible to link 2 projects that are related to each other?
RE: Linking different project plans
Hi Kamilla - thanks for your question. Yes it's possible. One way to do this is to create a new temporary project and from the file menu insert each project you want to link. Theyn drag links between the relevant tasks. Double click the links to set them to the type you want. Close and save all the files. Now the projects will be linked. You don't need to keep the temporary project you created. Hope this helps - let us know if you have any further quesitons.
Kind regards, Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Set default task type - Project 2010a. In Project, click on the File tab |