Baselines

resolvedResolved · Low Priority · Version 2007

Graham has attended:
Project Introduction course

Baselines

Is it possible to save more than one baseline for a project?

RE: Baselines

Hello Graham,

Thank you for your post, welcome to the forum;

Yes, you can save up to 11 baselines for a project

regards Pete


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.