finishend dates

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » Finish/end dates

Finish/end dates

resolvedResolved · Urgent Priority · Version 2003

Linda has attended:
Project Intro Intermediate course

Finish/end dates

Hi Guys,
Hope you are all well.

I am currently working on a project where there is an end date of mid 2009.

However there is also a much more important "go live" date which is much sooner of mid october 2008 from when the majority of tasks will be completed.

When the plan was initially created by someone, he based the plan from start date. As a result, when I want to look at the critical path, the system is only picking up tasks near the end date of mid 2009.

As a result, in my opinion the critical path doesn't give me an accurate reflection of the current situation.

Is my interpretation incorrect or is there another view which will let me determine tasks on the critical path? Or can I change the finish date and bring it in nearer to this mid-way point in the project?

thanks very much
Linda

RE: Finish/end dates

Hi Linda

Thank you for your question

The critical path derives from the logic of the individual task durations and the dependencies between them. As a consequence, if this information accurately reflects the situation, then the critical path is correct.

It seems to me however that you in effect have two projects.

One comprising the tasks prior to the go live date and another for the tasks after it.

If you split the project in this way, you should find that the critical path of the first project will show you those tasks critical to going live.

Hope this helps

Regards

Stephen

RE: Finish/end dates

Thank you very much Stephen. This has resolved my problem Best Regards Linda


 

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.

View all MS Project hints and tips


Server loaded in 0.12 secs.