lead times

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » Lead times

Lead times

resolvedResolved · Low Priority · Version 2007

David has attended:
Project Intro Intermediate course
Project Advanced course

Lead times

can you explain more about laed time, lag and negative lags.

RE: Lead times

Hi David

Thank you for your question

Lag time is where there is delay between the start or finish of a predecessor task and the start or finish of its sucessor. For example if 2 tasks are linked on a simple finish to start basis, and if the sucessor cannot start until 2 days after the predecessor is complete, then the relationship has a two day lag.

Lead time is the reverse of lag time. Imagine in the above example that it was possible to start the sucessor task not when the predecessor is complete, but when it is 50% complete. In this instance the relationship has a 50% lead. In MS Project lead times are entered as negative lags.

Hope this is useful

Regards

Stephen


 

MS Project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)

View all MS Project hints and tips


Server loaded in 0.08 secs.