Extra time to a task
Resolved · Low Priority · Version 2003
Jo has attended:
Project Intro Intermediate course
Extra time to a task
How do you add extra 'buffer' time to a task / reduce time on a task - not the number of days.
RE: Extra time to a task
Hi Jo
If I understand you correctly you might want to adjust how much work a resource will be carrying out on a task e.g. allowing 5 days duration for a task that takes perhaps an hour per day.
You can achieve this by switching to Resource Usage view and editing the assigned work for each task on a day by day basis.
I hope this is helpful. If you have any other questions please do not hesitate to contact us.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Keep constraining dates to a minimumAs far as possible avoid fixing the dates of your tasks. For example try to steer of clear dragging task bars in the Gantt chart to move them on the timeline or entering dates directly into the Start / Finish fields. |