Working time
Resolved · Medium Priority · Version 2003
Simona has attended:
Project Intro Intermediate course
Project Advanced course
Working time
I want to change working time to 24 h, so I am going to tools, change working time and selecting 24h calender, but before doing that , do I have to select all columns that have the time, because if just change it without selecting all date, when I access calendar again, it displays default calendar, can you explain how to handle this tool, regards, Simona
RE: Working time
If you already have tasks in your project, you cannot change the working time for these.
You need to define the 24 hour calendar BEFORE entering tasks.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Autofit column width – Project (all versions)At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move. |