Working time

I want to change working time to 24 h, so I am going to tools, change working time and selecting 24h calender, but before doing that , do I have to select all columns that have the time, because if just change it without selecting all date, when I access calendar again, it displays default calendar, can you explain how to handle this tool, regards, Simona

RE: Working time

If you already have tasks in your project, you cannot change the working time for these.

You need to define the 24 hour calendar BEFORE entering tasks.


 

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.

View all MS Project hints and tips


Server loaded in 0.1 secs.