microsoft project

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » Microsoft project

Microsoft project

resolvedResolved · High Priority · Version 2003

Graham has attended:
Excel Advanced course

Microsoft project

how can you move non working tome to the front o a bar?

RE: microsoft project

Hi Graham

Thank you for your question

If you click on format-timescale and in the resulting dialog box, click the non working time tab. You can then choose the option to draw non working time in front of the task bars

You can also use this view to have any bank holidays defined in your project default calendar appear as non working time. To accomplish this click on the calendar combo box and select your project default calendar.

Regards

Stephen


 

MS Project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.

View all MS Project hints and tips