Microsoft project
Resolved · High Priority · Version 2003
Graham has attended:
Excel Advanced course
Microsoft project
how can you move non working tome to the front o a bar?
RE: microsoft project
Hi Graham
Thank you for your question
If you click on format-timescale and in the resulting dialog box, click the non working time tab. You can then choose the option to draw non working time in front of the task bars
You can also use this view to have any bank holidays defined in your project default calendar appear as non working time. To accomplish this click on the calendar combo box and select your project default calendar.
Regards
Stephen
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Inserting Task Durations QuicklyWhen entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day. |