What are the definitions of float and lag?

RE: MS Project

Hi Mark

Thank you for your question

Float is the amount of time that the finish date of a task can be delayed before it delays either its successor tasks or the completion of the project. Free Float refers to the former and total float to the later. Obviously tasks on the critical path will have zero Float.

Note project uses the term slack to mean float, as this is the American term for it.

Lag is a specific delay built into a task dependency. For example, if you are sending out a mail shot and then processing the replies, you would link the two tasks as obviously you can


 

MS Project tip:

Use Autofill in MS Project

a. Complete 1st entry
b. Select cell with entry to be copied
c. Click & drag autofill handle over the lines to also contain the same information. (the autofill handle is the little black square in the bottom right hand corner of the heavy lack outline on the selected cell)

View all MS Project hints and tips


Server loaded in 0.11 secs.