Project - Show summary task detail

resolvedResolved · Low Priority · Version Standard

Alison has attended:
Project Intro Intermediate course

Project - Show summary task detail

HI , In our training we were informed that if we didn't set our projects to have a Zero task this would affect the calculations . We're just wondering what calculations they will affect .

Many Thanks

RE: Project - Show summary task detail

Hi Alison

Thank you for your question


I am assuming that by zero task you are referring to a milestone. I also assume that you are talking about the need for a final milestone, to which all tasks without natural successor tasks should be linked.

This is necessary to ensure scheduling continuity, whereby the final completion point of a project can easily be identified. Any task that is not linked to the final milestone


 

MS Project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.

View all MS Project hints and tips


Server loaded in 0.08 secs.