Gantt chart dates when going into a new calendar year
Resolved · Low Priority · Version Standard
Sally has attended:
Project Intro Intermediate course
Gantt chart dates when going into a new calendar year
I am retrospectively setting up a project plan which started in November 07. It won't end until the end of Aug 08. Although the task pane is correctly showing that tasks start in 08, the Gantt Chart goes from Dec 07 to Jan 07 (it changes to April 08 after March 07). Why is this happening?
RE: gantt chart dates when going into a new calendar year
Hi Sally
Thanks for your question
On the face of it this is rather puzzling. It could be a problem with your installation of project, or it may be something else that is not immediately obvious. It is difficult to judge without seeing the question
Can I suggest you email a copy of it to
stephenATmicrosofttrainingDOTnet
and I will have a look at it and get back to you
Regards
Stephen
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Avoid Accidental ConstraintsThe initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.) |