Split Task
what would be a typical use of "Split Task" ?
RE: Split Task
Hi Andi
Thanks for your question.
Split task is handy to show an activity that starts then for some reason will pause before resuming later on. There is a split task icon on the toolbar. It can also be activated by choosing Edit > Split Task
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Compare Work and DurationDuration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field. |