Split Task

what would be a typical use of "Split Task" ?

RE: Split Task

Hi Andi

Thanks for your question.

Split task is handy to show an activity that starts then for some reason will pause before resuming later on. There is a split task icon on the toolbar. It can also be activated by choosing Edit > Split Task

I hope this helps - do let us know if you have any further questions.

Kind regards,

Andrew


 