project server courses - Material resource

resolvedResolved · Low Priority · Version Standard

Olufemi has attended:
Project Intro Intermediate course
Project Advanced course
Project Intro Intermediate course

Material resource

How do I track a material cost if I want to input my values instead of using % complete? I would like to put in my spent cost values for the material resource. E.G if the fixed cost is

RE: Material resource

Hi Olufemi,

Thank you for your question.

If you are paying for a subcontractor's services at a series of points in the contract and you wish to reflect this, then you could mark those points as milestones in the project and attach fixed costs to those milestones. These costs would then be incurred as you hit them.
Note that in this instance the vendor's resources would have to have zero costs associated with them, otherwise they wiould be double charged.

Regards

Stephen


 

MS Project tip:

MS Project 2010 Scroll to Task

Ever feel lost on a large project file? In Gantt view, Task ribbon, Editing, click on the Scroll to Task tool to centre the task bar on your screen.

Shortcut Ctrl+Shift+F5

Same as Go to Selected Task in MS Project 2003.