london ms project server training - Task constraints
Resolved · Low Priority · Version Standard
Andrea has attended:
Project Intro Intermediate course
Task constraints
How do I set task constraints?
RE: Task constraints
Hi Andrea
Thankyou for your question
To set task constraints first select the task you want to modify, in the GANTT chart view, and open the task information dialog by double clicking on the task.
If you the select the advanced tab, you can choose a task constraint and a date for it in the relevant combo boxes.
Regards
Stephen
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Autofit column width – Project (all versions)At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move. |