RE: Tasks
Hi Alka
Thanks for your question
If you select the relevant task in the GANTT chart and then double click on it, the task information dialog will open.
Select the adavnced tab and you can access the task constraints from that point.
Regards
Stephen
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Email a TaskWhen you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system. |