Is it possiblke to link between seperate project plans

Ii.e a dependency reminder that is linked to a task on another project

RE: Dependency Linking

Hi Ava

Thankyou for you question

If you projects are using a common resource pool then if you open the resource pool, choosing the option to also open a master file; then you can link tasks across projects in the same way as within an individual project.

If the projects do not use a common resource pool, then you can open a blank project file and insert the individual projects into it using Insert-Project.

Once again at that point you can link tasks across individual projects as if they were in the same project

Regards

Stephen


 