exchange server 2003 distant learning - Microsoft Project

resolvedResolved · Low Priority · Version Standard

Jan has attended:
Project Intro Intermediate course

Microsoft Project

I would like to know if you could make particular tasks visible by colour in order to easily see individual tasks by person and not just task.

RE: Microsoft Project

Hi Jan

Thank you for your question

If you want to view individual tasks by person, the best solution is to use the resource useage sheet. This will allow you to identify the breakdown of task allocations by resource.

You can then filter by individual resource to see specific individuals.

In addition if you open the resource useage sheet, split the screen and then open the GANNT chart in the botttom pane, then the GANNT chart view will synchronize with the selections in the resource sheet

Regards

Stephen


 

MS Project tip:

Change default view – Project 2010

a. In Project, click on the File tab
b. Select General from left hand side (this should be the screen displayed by default)
c. Set the Default view dropdown box to your chosen option
d. Click OK to apply your changes

View all MS Project hints and tips


Server loaded in 0.07 secs.